Subject:
|
Consider Proposal for Air Conditioning System Replacement at Murray Park/Quest Elementary
|
District Goals:
|
Objective #6: Finance & Operations Address ongoing financial challenges by re-examining system processes for efficiencies that can drive resources into our core purpose of student learning.
* Fund Balance and Bond Rating
* Balanced Budget
* Efficient Operations
|
Enclosure
|
Attached is a memo detailing the proposal to replace the air conditioning unit at Murray Park/Quest Elementary School.
|
File Attachment:
|
|
Summary:
|
The District plans to replace the 33-year-old air conditioning system serving the main hallway, office, art, music, and library areas of Murray Park/Quest Elementary at an estimated cost of $115,000. The project will include a new outdoor condensing unit, evaporator coils, and upgraded refrigeration lines, with installation targeted for spring 2025. The District is currently finalizing a Request for Proposals to secure a vendor.
|
Budgetary Impact:
|
The project is estimated to cost approximately $115,000 and will be funded through the Long-Term Capital Improvement Trust Fund (46).
|
Recommendation:
|
|